AECC delivered the Al-Kadrh substation at Abu Sadad near Abha as a ten-bay indoor GIS facility spanning three voltage levels, 132/33/13.8kV. The project supplied five power transformers in total, three rated 67 MVA and two rated 70/55 MVA, alongside 40 circuit breakers of 13.8kV switchgear and four capacitor banks split across the 13.8kV and 33kV levels. The scope covered protection, control, SCADA, substation automation and telecommunications systems, with testing and commissioning completed before handover.