Loading

AECC carried out the interconnection works linking six 33kV substations across Al Qassim, substations 7802, 7803, 7808, 7818, 7841 and 7847, modifying and converting the existing switchgear feeders to support the new network configuration. The scope included a 14 kilometre route of 33kV underground and fibre-optic cable connecting substations 7818 and 7841.